Hyundai , Bechtel

Gulf of Suez Power Plant, EDF

Geotechnical Consultant and Pile Testing using NDT

  • The project was supported on deep piles reaching more than 28 m.

  • Piles diameters 1.1 – 1.5 m with capacity reaching 1000 tons.

  • Geotechnical Consultant for the design revision and pile testing.

  • Total Contract Value: 74M EGP

Client: Hyundai
Project Manager: Bechtel