Four Seasons at the Nile Plaza

Third Party for underground works Contractor (Hyundai)

  • A 5000 sq m in plan with 30 stories above ground and 12 m deep excavation right at the Nile shore.

  • Diaphragm wall with two layers of anchors and dewatering.

  • Piles and barrettes to sustain the building loads

  • Grouting was not needed due to the existence of a layer of clay at 25 m depth.

  • Total Contract value 20 M EGP

Client: Bechtel, Hyundai